Permits & Licenses
|
 |
Town
of Woodway Fee Schedule
| |
BUILDING/PERMIT
FEES |
FEE |
| 1. |
Building
Permit Fee
Based on Total Valuation (includes swimming pools and game
courts) |
| Total
Value |
Fee |
| $1
to $2,000 |
$85 |
$2,001
to
$25,000 |
$85 for
the first $2,000 plus $17.50 for each additional $1,000
or fraction thereof |
$25,001
to
$50,000 |
$490
for the first $25,000 plus $12.60 for each additional
$1,000 or fraction thereof |
$50,001
to $100,000 |
$805 for
the first $50,000 plus $8.75 for each additional $1,000
or fraction thereof |
$100,001
to
$500,000 |
$1,243
for the first $100,000 plus $7 for each additional $1,000
or fraction thereof |
$500,001
to
$1,000,000 |
$4,043
for the first $500,000 plus $6 for each additional $1,000
or fraction thereof |
| $1,000,001
and up |
$7,043
for the first $1,000,000 plus $2.80 for each additional
$1,000 or fraction thereof |
|
| 2. |
Plan
Check Fee |
65%
of Building Permit fee |
| 3. |
Inspections |
Included
in BP fee |
| 4. |
Mechanical
– New SFR |
$175
up to 2,000 sq. ft.
$275
for 2001 - 3,000 sq. ft.
$375
for 3001 - 4,000 sq. ft.
$475
for 4001 - 5,000 sq. ft. |
| 5. |
Plumbing
– New SFR |
$175
up to 2,000 sq. ft.
$275
for 2001 - 3,000 sq. ft.
$375
for 3001 - 4,000 sq. ft.
$475
for 4001 - 5,000 sq. ft. |
| 6. |
Remodels
(based on number of fixtures) |
$75
for 1 fixture
$125
for 2 to 4 fixtures
$175
for 5 to 7 fixtures
$225
for 8 to 10 fixtures
$275
for 11 to 13 fixtures
$325
for 14 + fixtures |
| 7. |
Fence |
Based
on valuation |
| 8. |
Side
Sewer Fee |
$1070
adjusted annually |
| 9. |
Tributary
Lot Fee |
$914,
adjusted annually |
| 10. |
Right
of Way – Routine Utility |
$150
+ $250 deposit |
| 11. |
Right
of Way – Major Utility |
$200
+ $250 deposit + costs |
| 12. |
Right
of Way – Private Homeowner |
$125
+ $200 deposit + $250 engineer fee |
| 13. |
Roofing |
If
necessary, based on valuation |
| 14. |
Review
of Building Official’s Decision |
$150
per application |
| 15. |
Demolition
Permit |
Minimum
$250, based on valuation |
| 16. |
Code
Interpretation |
$100
plus costs |
| 17. |
Outdoor
Burning |
Prohibited |
| 18. |
Re-inspection
fees assessed under 108.8 |
$60/hour |
| 19. |
Other
building inspection fees not listed |
$60/hour |
| 20. |
Additional
Building Plan review required by changes, additions or revisions
to plan |
$60/hour,
minimum ˝ hour |
| 21. |
Building
permit operational fee, based on total valuation |
| Total
Value |
Fee |
| <$10,000
|
$25 |
| $10,000-$250,000 |
$125 |
| >$250,000 |
$250 |
|
| 22. |
Other
plumbing inspection fees not listed |
$50/hour |
| 23. |
Additional
Plumbing or Mechanical Plan review required by changes,
additions or revisions to plan |
$50/hour,
minimum ˝ hour |
| 24. |
Renewal
of expired building permit |
˝
of original building permit fee, plus operational fee, state
fee, & plan review if deemed necessary by Building Official |
| 25. |
Moving
of Building |
$75
plus deposit if necessary |
| 26. |
Installation
of a moved residential structure onto a new site, including
the foundation, water hookup and the building drain connection |
$250 |
| 27. |
Grading
Plan Review Fees |
50
cubic yards - No fee
51
to 100 cubic yards - $47.00
101
to 1,000 cubic yards - $74.00
1,001
to 10,000 cubic yards - $98.50
10,001
to 100,000 cubic yards:
$98.50 for the first 10,000 cubic yards
plus $49.00 for each additional 10,000 yards or fraction
thereof
100,001 to 200,000 cubic yards:
$539.50
for the first 100,000 cubic yards
plus $26.50 for each additional 10,000 cubic yards or fraction
thereof
200,001 cubic yards or more:
$804.50
for the first 200,000 cubic yards
plus $14.50 for each additional 10,000 cubic yards or fraction
thereof
|
| 28. |
Grading
Permit Fees |
50
cubic yards - $47.00
51 to 100 cubic yards - $74.00
101
to 1,000 cubic yards:
$74.00
for the first 100 cubic yards
plus $35.00 for each additional 100 cubic yards or fraction
thereof
1,001 to 10,000 cubic yards:
$389.00
for the first 1,000 cubic yards
plus $29.00 for each additional 1,000 yards or fraction
thereof
10,001 to 100,000 cubic yards:
$650.00
for the first 10,000 cubic yards
plus $132.00 for each additional 10,000 cubic yards or fraction
thereof
100,001 cubic yards or more:
$1838.00
for the first 100,000 cubic yards
plus $73.00 for each additional 10,000 cubic yards or fraction
thereof
|
| 29. |
Additional
grading plan review or review of specialized reports required
by changes, additions or revisions to approved plans |
$100/hour
(minimum ˝ hour) or actual cost |
| 30. |
Storm
Drainage and Erosion Control facilities and inspections
and plan review |
$75/hour
plus engineering review costs |
| B. |
LAND
USE FEES |
FEE |
|
1. |
Short Plat |
$1,500 plus $100/lot + costs |
|
2. |
Variance |
$1,000 plus costs |
|
3. |
Boundary Line Adj. |
$500 plus costs |
4.
a.
b. |
Comp Plan Amendment
Site Specific
Text Amendment |
No Fee
Both or either $1,000 plus costs
$1,000 plus costs |
|
5. |
Zoning Ordinance Amendment |
$1,000 plus costs |
|
6. |
Wireless Facility Fee |
$4,000 plus costs |
|
7. |
Appeals |
$500 plus costs |
|
8. |
SEPA |
$500 plus costs |
|
9. |
Code Interpretation (complex) |
$100 plus costs |
|
10. |
Site Plan Review |
$250 |
11.
a.
b. |
Long Sub-Division
Preliminary Plat
Final Plat
|
$2,000 base plus $100/lot + costs
$1,500 base plus $50/lot + costs |
| C. |
LICENSES/OTHER
FEES |
FEE |
|
1. |
Business License |
$50 |
|
2. |
Home Occupation License |
$50
Delinquency fees:
15-30 days: $10/day
31-90 days: $25/day
>90 days: $100/day |
3.
a. |
Dog License
Lifetime |
$5.00
One time fee per above |
|
4. |
Audio Tapes |
$5.00 plus tape |
|
5. |
CD |
$10.00 |
|
6. |
Sign Permit |
$50 |
|
7. |
Insufficient Funds Fee |
$30 |
|
8. |
Copying public records |
$.15/page for letter or legal size;
actual cost for larger |
|
9. |
False Alarms |
$250/each response within 6 months |
|